Facility;Client;Development Stage;Year;Note
ZMТ-250 Motor Fuel Refinery;Lukoil-Kogalymneftegaz Company, Kogalym;Construction Feasibility Study;1994-1995
ZMТ -200 Motor Fuel Refinery;ЧМЗ Production Corp., Glazov,Udmurtia;Construction Feasibility Study;1996
1,500,000 tpy Refinery;LUKOIL-Arktik-Tanker Company, Murmansk;Construction Feasibility Study;1997
ZMТ-500 Motor Fuel Refinery in Kopeisk; Oil-Service Company, Chelyabinsk;Construction Feasibility Study;1997
500,000 tpy Motor Fuel Plant in Bolshoy Kamen;Far East Oil Company;Construction Feasibility Study Report;1997
Upgrading of Samotlor Refinery;Tyumen Oil Company, Nizhnevartovsk, Research and Production Corp., Nizhnevartovsk;Check Calculations of Equipment for Revamping Project;1999
Upgrading of fuel production part at Petrotel LUKOIL Refinery;LUKOIL-Romania, Bucharest, Romania;Business Plan;1999
Upgrading of Ukhta Refinery;LUKOIL-Rostovneftekhimproekt Company, Rostov-on-Don;Development of the Process Part of Business Plan;2000
Construction of 3,000,000 tpy Primorsky Refinery, Leningrad Region;Mariisky Machine-Building Plant;Preparation of Declaration of Intent for construction investment;2001
Rebuilding of Astrakhan gas processing plant in terms of design development of control system connection;Astrakhan gas processing plant, Astrakhan Gasprom;Detailed Design Documentation;2003;Commissioned in 2004
Motor fuel refinery. Construction, stage II;LUKOIL-West Siberia, Refinery within Kogalymneftegaz Company;Updating of Feasibility Study;2003
Elaboration of proposals on development of crude oil refinery (1.8 mln and 2.5 mln tons/year);Khersonneftepererabotka Company, OC Alliance, Ukraine;Proposals;2003
Declaration of Intent on investment in construction of oil refinery in Vyborg area of Leningrad Region;VNP Ltd, Vyborg;Declaration of Intent;2003
Declaration of Intent on Investment in Construction of Deep Oil Refining Complex at Khabarovsk Refiney;Alliance Group;Declaration of Intent;2004
Feasibility Study (studiya proekt) on Construction of Hydroprocessing Complex at Khabarovsk Refinery;Alliance Group;Feasibility Study (studiya proekt);2004-2005
Declaration of Intent on Construction of 1,000,000 tons/year Oil and Gas Complex at Usinsk Region of Komi Republic;Usinsk Refinery, Usinsk;Declaration of Intent;2006
BEDD preparation for design of Ulan-Bator Refinery with 2 million tpy capacity;Vostokneftegas Company;Feasibility Study;2007
Pre-engineering study, collection and preparation of basic data for construction of Tyumen Refinery with 3 million tpy capacity;Tehneftinvest Company, Tyumen;Pre-engineering study; 2007
Pre-design preparation for construction of gas-condensate processing plant with capacity 600,000 tpy in Tikhvin;AVRO Company;Pre-engineering study;2007-2008
Phased transfer of Khabarovsk Refinery consumers to use of natural gas;Khabarovsk Refinery, OC Alliance;Technical and economic estimation;2007
Pre-engineering study and elaboration of technical and economic estimation for refinery of 2.5 million tpy in Volkhov;Volkhovneftekhim Companym, Volkhov;Pre-engineering Study. Technical and Economic Estimation;2007
Updating of Feasibility Study (studiya proekt) to split Hydroprocessing Complex construction in revamping Khabarovsk Refinery into 4 phases;Khabarovsk Refinery, OC Alliance;Feasibility Study (studiya proekt);2008-2009
Execution of General Designer functions at Chudovo Refinery;AVRO Company;;2008-2009
Reconstruction of LLC “Ilskiy Refinery”;LLC “Ilskiy Refinery”;Technical and Economic Calculation;2012
Delayed Coker Unit, Kstovo Refinery;McDermott, Netherlands;Detailed Design Documentation. Procurement Support;2019-2022