22-02-2022

Positive conclusion of Main State Expertise

Conclusion № 61-1-1-3-009321-2022
Positive conclusion of Main State Expertise of Project Documentation is obtained for facility “JSC Novoshakhtinsk Refinery. Construction of Advanced Oil and Medium Distillates Refining Complex.
Combined Hydrocracking Unit (capacity 2 571 thous. tpy) with Hydrogen Production Section (capacity 70 thous. tpy) and off-site facilities”.

Expertise conclusion No. 61-1-1-3-009321-2022.

Combined Hydrocracking Unit is designed by PMP Head Office in Saint-Petersburg, off-site facilities are designed by PMP Branch Office in Rostov-on-Don.

Construction of Advanced Oil and Medium Distillates Refining Complex is part of Novoshakhtinsk Refinery modernization program, implementation of which will allow to increase the oil refining efficiency up to the level of minimum 85-90%.